Contractor: Road Engineering Consortium - MOPC

Project: Paved type paving - Ypacarai - Pirayu, Route 1, Thompson Colonies Preparation of the Environmental Impact Assessment Study

Contract amount: 8.400 U$

Period: Year 1994

Amount of the work: $ 1,600,000

Description of the consultancy:
  • Collection and analysis of existing information.
  • Definition of the area of influence and operational area of the project.
  • Definition of the initial state of the environment of the current area without the project.
  • Identification and linking of environmental aspects related to the project and the activities of its works.
  • Description of an environmental forecast.
  • Determination of the potential impacts and impacts of the project.
  • Development of a management plan to mitigate the possible negative impacts of the project on the environment at its different stages.